
|
|
Update on the Desire Streetcar Project
By Sue Klein
Some disturbing and confusing information has come our way recently
regarding the Desire Streetcar Project planned for North Rampart Street and St.
Claude Avenue. Mr. William Gimple of Parsons Brinckerhoff, an engineering firm
specializing in rapid transit systems around the world, gave a presentation at
the May 20th Vieux Carré Commission meeting, where he showed the three
variations of track placement for the up and down river tracks along N. Rampart
Street (Plans A, B1, B2 - see map on next page). Also, at that time we learned
that the Basin Street loop is again being considered, whereby instead of the
streetcar going down Canal Street to turn around near the ferry, it would go up
to Basin Street and come back onto N. Rampart via Toulouse Street.
Mr. Gimple was making the presentation to the VCC because the VCC had just
been made a "consulting party" as part of the Section 106 process.
The Section 106 regulations of the National Historic Preservation Act were
established to protect historic properties, especially National Historic
Landmarks such as the Vieux Carré. This appears to be a flaw in this
particular Section 106 process, because the VCC should have been part of the
Section 106 process from the beginning.
FQCP presented our arguments for eliminating Basin Street and adopting Plan
B2 for track placement. To allow for further study, the VCC deferred a vote on
this issue until their June 17th meeting.
Later that day, I was told that RTA would make its decision on track
placement by June 6th, knowing that the VCC would not meet again until after
that date. Why would the VCC be approached for input, and then not be given
time to reply? Following e-mails and telephone calls to Councilwoman Clarkson,
the VCC, the RTA and Parsons Brinckerhoff officials, the date of June 6th has
been pushed back. Margaret Slater of Parsons Brinckerhoff in Nashville, who
gave the Section 106 presentation in April at the Maison Dupuy Hotel, has said
that no determination will be made until the VCC has given their input.
For those of you who may not be aware of this project, I have listed below
some of the pertinent issues at this time:
- Public meetings have been taking place for almost three years, but no
French Quarter resident groups were invited to participate until FQCP found out
about the project last December and applied and became a consulting party.
- A consensus of FQCP, VCPORA, Esplanade Ridge & Tremé Civic
Association, Bywater Neighborhood Association, Faubourg Marigny Improvement
Association, and Rampart Street merchants including William B. Allen and the
Saenger ALL favored the FQ Plan B2 track placement. That placement, as
Councilwoman Clarkson is aware, is for the upriver (Tremé) track to be
in the street and the downriver (FQ) track to be in the neutral ground --- with
the return loop being on Canal at the River --- not Basin Street! The Canal
Street loop (Canal to River) would allow riders to arrive at hotels and
shopping without transferring. Also, riders could continue to the Westbank via
the pedestrian ferry.
- The Basin Street loop via Toulouse to Rampart would be a traffic disaster,
since this is the main artery from I-10 into the French Quarter. At peak
traffic, the RTA is going to run streetcars every four minutes. Toulouse Street
between Basin and Rampart is used for police parking which would be lost, and
the stretch would only accommodate the length of one streetcar.
- As noted by William Gimple, the French Quarter is the only neighborhood
along the proposed route that has National Historic Landmark status and
therefore is entitled to preferential treatment.
- Landscaping and green space will exist regardless of track placement.
- Any track in the street on the French Quarter side would increase noise
& vibration (even though the new design is less intrusive than the old
tracks on St. Charles).
- There are safety issues regarding service to the French Quarter by fire,
police, and medical entities.
- Many more vehicles and pedestrians enter the French Quarter versus
Tremé. From a tourism management standpoint, this will increase traffic
congestion to an already overburdened French Quarter.
- In addition to the Federal money split being decreased to 50%, there is an
additional budget cut from $110 million to $80 million. By eliminating Basin
Street, a minimum of $1.2 million would be saved. Also, William B. Allen has
said they would relocate to Jefferson Parish, if tracks are laid on Basin
Street. The residents and the merchants are opposed to Basin Street, in
addition to costing more money. So, why is the RTA or the Department of Public
Works pushing Basin Street?
- The French Quarter side of Rampart has many on-street parking spaces.
Right now, traffic stops in the right lane when people parallel park. If
parking occurred as the streetcar stopped (if tracks were in the street on the
FQ side), then both lanes of traffic would be stopped at the same time.
- Also, we challenged the Parsons Brinckerhoff traffic studies and proved
them wrong. That is, the downriver (FQ) PM traffic is heavier than the upriver
(Tremé) AM traffic. This is another reason to keep the tracks out of
Rampart on the French Quarter side.
- Councilwoman Clarkson supports our consensus position for no Basin Street
loop and for the downriver (FQ) track being in the neutral ground and the
upriver (Tremé) track being in the left lane of N. Rampart.
- Our consensus group wants the Desire Streetcar, but with the least amount
negative impact to the Vieux Carré.
Trying to keep up with this project is difficult, because so many entities
are involved, and nothing is carved in stone yet. Our organization will keep
you updated, so stay tuned.
|
|